Major Change Status

No known major changes have been scheduled for the next 5 days.
Daisy’s full change process has been completed including implementation, test and back-out plans which have been reviewed by senior technical reviewers and management. Please contact the service desk quoting the change number if you have any queries.
No major changes scheduled
Change NumberTypeImpact StatementRisk StatementPlanned StartPlanned End
CHG0161183normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.29 April, 2024 8:00 am29 April, 2024 8:00 pm
CHG0154552normalTotal loss of service for anticipated impact durationServices should be considered at risk for the duration of the maintenance window.3 May, 2024 8:00 am3 May, 2024 7:00 pm
CHG0154547normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 8:00 am30 April, 2024 7:00 pm
CHG0161794normalTotal loss of service for maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 11:00 am1 May, 2024 11:00 am
CHG0154551normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.2 May, 2024 8:00 am2 May, 2024 7:00 pm
CHG0154549normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.1 May, 2024 8:00 am1 May, 2024 7:00 pm
Change NumberTypeImpact StatementRisk StatementPlanned StartPlanned End
CHG0161650normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.2 May, 2024 11:30 pm3 May, 2024 5:00 am
CHG0161451normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.29 April, 2024 9:00 am29 April, 2024 5:30 pm
CHG0161502normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 9:00 am30 April, 2024 3:00 pm
CHG0161435normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.30 April, 2024 9:00 am30 April, 2024 4:00 pm
CHG0162013emergencyService degradation for maintenance window durationServices should be considered at risk for the duration of the maintenance window.26 April, 2024 8:00 pm26 April, 2024 10:00 pm
CHG0161925normalNo impact to service is anticipated during the maintenance windowServices should be considered at risk for the duration of the maintenance window.2 May, 2024 9:00 am2 May, 2024 1:00 pm
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled
No major changes scheduled